Project Update:

Building B-North: Shoring and Excavation Underway

Mass excavation has begun on site and temporary shoring installation has been completed for the first lift of excavation. Work has started on the second lift of shoring and excavation and we should be hitting the bottom of the hole within the week. Once that is complete we will begin excavating for footings and the elevator pit.

-Update by Walsh Construction