Project Update:

Building B-North – New Year Update

Happy New Year!

It’s been a busy month for Capitol Hill TOD Building B-North. After completing the excavation and vertical concrete walls, we hit our first big milestone: the north slab on grade has been poured!

Now, as we begin preparation for the South half of our Slab on Grade, we are getting a head start on our Level 1 concrete deck.